The Scottish Courts have given an interesting decision in relation to IT contracts, relating to the allocation of delivery risk between supplier and customer and the importance of doing what it says in the contract.
In David MacBrayne Limited v Atos IT Services (UK) Limited (2018), Atos, a supplier, had entered into an agreement with David MacBrayne Limited to supply a digital platform. The engagement was not successful and the parties claimed and counter-claimed against each other for material breach of the contract (amongst other things).
Customer Dependencies – Whose Responsibility is Delivery?
IT contracts will often include dependencies on
Continue Reading IT Contracts Case Law Update: Allocation of Delivery Risk